Current Projects
Dairi,
North Sumatera
Bitung,
North Sulawesi
Subawa,
West Nusa Tenggara
Dieng,
Central Java
- Size 92MW On-Shore Wind
- Project Cost US$144 mio
- Has obtained survey licenses and permits
- Completed Preliminary Studies
- Size 63MW On-Shore Wind
- Project Cost US$98 mio
- Prefeasibility studies completed
- Local logistic survey conducted
- In discussion with PLN subsidiaries
- 200MW Off-grid Solar PV Power Plant
- Project Cost US$151 mio
- Mining company as an potential offtaker
- Site visit conducted
- MOU with landowners signed
- Size 24MW Ultra-low-pressure Geothermal
- Will acts as an added capacity to the existing power plant
- Project Cost US$43 mio
- Expected to generate 163 GWh of energy per year
- MOU with power plant owner signed
Experience
Aceh Wind,
Sumatera
Endikat Hydro
De-dieselization
Program - East Cluster
Nias,
Sumatera
- Size 55 MW On-Shore Wind
- Project Cost $135 mio
- Local Permits are available
- Consistently high wind resources
- Complete FS and Grid studies
- Include in the RUPTL
- Size 55 MW Hydro
- Project Cost US$155 mio
- Complete FS and ESIA studies
- EPC tendering is on going
- Include in the RUPTL
- Local permits are available
- Size 102 MWp PV & 252 MWh BESS
- Project Cost US$235 mio
- Winning bidder awarded
- LOI has been signed
- Included in the National Strategic Project
- ESIA consultant selection is on going
- On going PPA discussion with PLN
- Size 6 MW PV & BESS
- Project Cost $15 mio
- Local permits are available
- Complete FS and Grid studies
- Included in the RUPTL firm project list
- Land acquired via down payment
- Actively pusuing into the bid stage